335,026 kr
Fixed offer
Actual Spend
-- kr
-- % of quote
Gross Margin
-- kr
-- % margin
Hours Tracked
-- h
-- of estimated
STARK Materials
-- kr
-- invoices
Budget Consumed
-- %
of 335,026 kr
Quoted vs Actual
Spend Distribution
Offer Breakdown
STARK Invoices
Financial Summary
| Category | Amount (kr) | % of Quote |
|---|---|---|
| Loading... | ||
STARK Materials - Invoice Details
| Date | Invoice No. | Description | Amount (kr) |
|---|---|---|---|
| Loading... | |||
Hours Comparison - Estimated vs Actual
| Task / Area | Estimated (h) | Actual Tracked (h) | Variance (h) | % Complete |
|---|---|---|---|---|
| Loading... | ||||
Work and Materials
OfferÂ
Floors:
Demolition – 11400kr.
Work – 8000kr.
Materials – 3400kr.
Floor construction – 122917kr. – Straightening of main framing. Installation of floor heating plates and floor heating pipes and subflooring.Â
Work – 50250kr.
Materials – 72557kr.
Finish floor herringbone type small with glue sanding and finish coating – 400kr. m2Â
140m2 * 400kr. = 56000kr.
Tiles – 10000kr.
Walls – 118209kr. – Plastering, sanding, felt and paint
Work – 83250kr.
Materials – 34959kr.
Total – 318526kr.
Â
Extra workÂ
Â
Demolition – 6500kr.
Kitchen and chimney
Floor insulation 10000kr.
Work – 5000kr.Â
Materials – 5000kr.
Total – 16500kr.Â