Stubbegårdsparken 131
By
Sorvan
Revit Model
Architectural drawings
Kitchen
Materia that we have piked
Payment overview
Technical drawings
Work photos
It will be updated soon with more pictures
Material Keneth house
Price – 618.145 + 154.536 Vat = 772.681 kr. – 103.700 euro
I got – 256.000 + 64.000 Vat = 320.000 kr. – 43.300 euro
I Have left – 452.681 – 60.800 euro
What I need to spend – 329.992kr. – 44 .170 euro
Buffer of 124.242 kr. – 16.630 euro
Foundation – 83.864 kr. – 11.260 euro
General / foundation materials
- Concrete – 5 m³
- RC BETON Scan Blok, 19 cm x 33 cm x 49 cm – 208 pcs + adhesive/glue
- RAW plywood (packaging grade), 9 mm x 1220 x 2440 mm – 10 pcs
- RAW roof battens C18 BDT, 38 x 73 mm, 4200 mm – 20 pcs
Concrete slab materials
- RAW stabilgrus (sub-base gravel) BigBag 0–32 mm, 500 L – 10 pcs
- RAW EPS RE80 floor insulation boards, 150 mm, 600 x 1200 mm – 180 pcs
- ALPHA moisture & radon barrier, 2 m x 40 m – 2 rolls
- Concrete – 13 m³
Wall – 25.570 kr. – 3.432 euro
If we what this wood I need 1000 euro on top of the budget.
Thermowood * 19 x 4.200 x 188
Roof – 36.010 – 4.820 euro
Roof membrane – Мембрана Metalik 450gr/m2
Roof tape – Мембрана Dupont Tyvek Hosewrap
Metal roof plates and parts – 16 euro per m2 – 120 m2 – 2000 euro
Osb plates
Bathroom – 29.884 kr. – 4.000 euro
Sink, toilets, shower, wall plates, boiler and more.
Kitchen – 29.884 kr. – 4.000 euro
Cabinets and appliances
Floor heating 29.884 kr. – 4.000 euro
Pump and pipes
Windows – 22.413 kr – 3.000 euro
What’s left to pay
Transport – 37.355 kr. – 5.000 euro
Bulgaria / Denmark
Connection fees – 35 000 kr. – 4.685 euro
Water and EL
Finishing materials
Floor – 40.000 kr.
Natural wood floor in living room corridor
Laminate floor in sleeping room
Walls finish – 10.000kr.
Plywood – the price of materials have gone up so I need 5.000 kr. more
Ceilings – 20.000 kr.
TROLDTEKT all house
Paymentplan
Payment
1 – 20 000 kr. February – 16 – 20
For small stuff
Payment 2 – 130 000kr. March – 02 – 06, if we can do it before if will be perfect.
Forpluming
Walls
Roof
Windows
Kitchen
Payment 3 – 155 000 kr. End of march beginning of April Depending on the weather
Transportation
Foundation
Connection
fees
Payment 4
– End of march we will decide it when I’m in Denmark
Finishing
materials
Payment 5
– around 145 000 – When the house is finished
SORVAN DESIGN
Project Dashboard
Stubbegårdsparken 131 • 4900 Nakskov
In Progress Dec 14, 2025 – May 31, 2026TOTAL BUDGET
772,681
DKK incl. VAT
INVOICED
465,821
DKK (60.3%)
REMAINING
306,860
DKK to invoice
HOURS
1,307
of ~2,000 estimated
TIMELINE
61%
102 of 168 days elapsed
Project Timeline
Dec 14, 2025 — Project Start
Construction begins in Bulgaria. 2-person crew on site daily.
Feb 12, 2026 — STARK Materials Offer
First STARK offer received (83,864 DKK). Foundation materials quoted.
Feb 16–20 — Payment 1 (20,000 DKK)
Small materials purchased.
Mar 2–6 — Payment 2 (130,000 DKK)
Major materials: plumbing, walls, roof, windows, kitchen.
Mar 25, 2026 — Current
1,307 hours logged. Preparing for foundation phase.
Apr 13, 2026 — Foundation Start
On-site foundation work begins in Nakskov. STARK delivery coordinated.
Late Apr — Payment 3 (155,000 DKK)
Transport, foundation, connection fees.
May 2026 — Assembly & Finishing
House assembly on foundation. Interior finishing begins.
May 31, 2026 — Target Completion
Final inspection. Payment 5 (~145,000 DKK) upon handover.
Timeline Progress
Hours vs Estimate
Hours Logged
| Period | Hours |
|---|---|
| Dec 2025 (from 14th) | ~216 |
| Jan 2026 | ~372 |
| Feb 2026 | ~336 |
| Mar 2026 (to 25th) | ~383 |
| Total | 1,307 hrs |
Projection
Estimated total: ~2,000 hrs
Completed: 1,307 hrs (65%)
Remaining: ~693 hrs
Days left: 67 days
Avg needed/day: ~10.3 hrs/day
Financial Overview
Total Contract
772,681 DKK
Invoiced to Date
465,821 DKK
Remaining
306,860 DKK
Invoices
| # | DKK | EUR | Status |
|---|---|---|---|
| 19 | 19,862 | 403 | Paid |
| 20 | 158,656 | 3,216 | Paid |
| 24 | 99,091 | 2,009 | Paid |
| 26 | 19,817 | 402 | Paid |
| 27 | 19,817 | 402 | Paid |
| 29 | 19,817 | 402 | Paid |
| 30 | 128,761 | 2,610 | Paid |
| Total | 465,821 | 9,443 |
Cost Breakdown
Materials & Construction
~420,000 DKK
Labour (Bulgaria)
~180,000 DKK
Transport & Logistics
~90,000 DKK
Foundation (DK)
~83,864 DKK
Payment Plan
Payment 1 – 20,000 DKK
Feb 16-20 – Small materials
Payment 2 – 130,000 DKK
Mar 2-6 – Plumbing, walls, roof, windows
Payment 3 – 155,000 DKK
End Mar / Apr – Transport, foundation, connections
Payment 4 – TBD
Decided on-site in Denmark
Payment 5 – ~145,000 DKK
When house is finished
Materials Selected
Last updated: March 25, 2026 • Sorvan Design